Wednesday, July 30, 2014

Back in Effect

Been back a few days and a lot has changed. We're into the picking of fine details (door and window trim, styles for doors and hardware, etc.) and sheetrock is up!

NEXT:

  • Front deck going in hopefully by next Tuesday if labor can be scheduled
  • Cabinet installation starts on Wednesday
  • Concrete forms go in tomorrow and slabs will be poured Friday
  • Meeting with lighting designer on Friday
  • Finishing out all tile/wood/quarz choices this week
  • Painters will arrive after the doors are in (2 weeks out) or after flooring is in, whichever lines up best
  • Back deck will be squeezed in at some point, possibly whilst front deck is happening


Front deck might need a handrail now since the shift of the footprint to the south makes the south end around 30" off the ground. We will wrestle with that in the days ahead, as it may increase costs.

No comments:

Post a Comment